Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
  • A\frac{1}{2}
  • B\frac{3}{4}
  • C1
  • D\frac{11}{4}
  • E\frac{11}{2}
显示答案
正确答案: C